PS: Kenya's China Gezhouba-built Thwake Dam 94.2% complete, impoundment due April 2027

Thwake Dam, on the Makueni–Kitui county border, is 94.2% complete, and water impoundment is set to begin in April 2027. Julius Korir, Principal Secretary for Water and Sanitation, told the National Assembly Departmental Committee on Blue Economy, Water and Irrigation on 10 November, The Star reported on 14 November. Capital FM carried the same briefing on 13 November.

An African Development Bank (AfDB) field report dated 21 October put progress at 94%. Korir gave the same 94.2% figure in September 2025, the Kenya News Agency (KNA) reported at the time. In October 2025 the agency reported that impoundment was expected during the October–November rains this year.

Both outlets' headlines call the scheme a KSh 100 billion project, about US$770 million at the Central Bank of Kenya rate of KSh 129.96 to the dollar on 12 November.

China Gezhouba Group Company is building the dam. KNA reported on 16 October 2025 that the AfDB's director general for the East Africa region praised the quality of its construction work. AidData lists China Gezhouba Group Company Limited as the engineering, procurement and construction contractor, with a commercial contract signed with the Kenyan government on 15 November 2017.

Korir said: "When we ran short of cash, we engaged with our development partners, and they allocated additional funding." Both outlets say the AfDB provided additional financing. Korir said the government's commitment to completing the dam is "very evident".

The dam stands at the confluence of the Athi and Thwake rivers. It is about 80.5 metres high and designed to store 688 million cubic metres of water.

The programme has four phases. Phase one is the dam and associated infrastructure. The later phases cover hydropower, water supply and sanitation, and irrigation.

The plan includes 20 MW of hydropower and irrigation for 40,000 hectares, about 100,000 acres. Once the water supply component is running, the scheme is to supply about 150,000 cubic metres of treated water a day to roughly 1.3 million people in Makueni and Kitui counties and Konza Technopolis in Machakos County.

Martin Kimeu, a Wote resident, said, as quoted by Capital FM: "Ukambani is fertile. Water has been the biggest impediment to the realization of our agricultural potential." The Star quoted him as saying Thwake Dam water "is the clear solution to this".

Drafted and translated with AI assistance; reviewed and published by editor . How we use AI

Sources

Reporting Desk research, human-reviewed Sources 6 Published 14 Nov 2026 Corrections none How we check

  1. Sh100 billion Thwake Dam project nears completion the-star.co.ke about
  2. Ukambani region rallies behind Sh100bn Twake Dam project capitalfm.africa
  3. AfDB applauds Thwake Multi-Purpose Dam progress (Kenya News Agency, 16 October 2025) kenyanews.go.ke about
  4. Thwake dam in final stages of completion (Kenya News Agency, 25 September 2025) kenyanews.go.ke about
  5. Thwake Multi-Purpose Water Development Program, Phase 1 (AidData) china.aiddata.org
  6. Central Bank of Kenya indicative exchange rates, posted 12 November 2026 centralbank.go.ke about

Got a tip? Tell us →

Sign in to comment →